 |
 |
|
|
|
Anglian Water’s Biggest Ever Project

|
|
The finalization of the Wing
Extension project is Anglian Water’s biggest ever
project, providing drinking water to over a million
people. Andrew Jordaan from Mott Macdonald Engineers
became involved in the project nearly two years ago.
He produced the preliminary and final designs for 40
kilometers of the new pipeline on South African
infrastructure software design package Civil
Designer.
|
|
|
Andrew Jordaan is a South African
civil engineer with extensive experience in various
high-level projects. When the opportunity arose to
practice these skills at the UK based Mott MacDonald,
he grabbed the opportunity with both hands and hasn’t
looked back since.
The Wing Water Treatment Works extension began in 2005
when Anglian Water indicated its plans to abstract
more water from Rutland Water and extend the existing
Water Treatment Works at the Wing for further water
supply to the population. With the emergence of 90 000
additional homes, the project finally got off the
ground.
Andrew explains: “Anglian Water had to extend its
existing water treatment works at the Wing to provide
drinking water to meet the increase in consumption.
This meant that the new underground pipelines had to
be laid from Rutland Water to the Wing extension and
from the Wing to Kettering via Corby.”
Rutland Water was built as a reservoir in 1975 to
store and provide water for treatment in the supply of
domestic and commercial users. Prior to the
commencement of the project, the existing pipelines
and water treatment works were capable of taking up to
75% of the amount of water that Anglian Water was
permitted by license. With the proposed extensions,
Anglian Water will be able to extract up to the full
licensed amount from Rutland Water.
Rutland Water’s wetland area is protected by law as a
Special Protection Area. Due to this legal
environmental protection, Anglian Water is obligated
to ensure that future plans for water provision
incorporate the protection of special wildlife of the
reservoir.
The team of designers therefore created additional
lagoons and wetlands as an alternative habitat for
wildlife during periods of lowered reservoir levels.
They also constructed additional dams in the existing
reservoirs to maintain water levels in bays during
lowered levels in the main reservoirs. |
|
|
The legal environmental protection on the project
placed considerable limitations on the design team.
Fortunately these obstacles did not present any
problems while working in Civil Designer. “The program
automatically picked up the long sections off the DTM
without any user intervention. We used the aerial
pictures as a background and placed the contours and
cadastral plans over it to plan and plot the routes.
The pipelines were laid across agricultural land and
involved crossings of railways, roads and rivers.”
“The software was therefore instrumental in helping us
complete the preliminary designs, feasibility studies
and DTM which extended into the final design for the
tunnel crossings of the major roads and railways,”
explains Andrew.
The construction of the Water Treatment Works and the
laying of the pipelines will be completed in March
2010. It will supply an average of 50 million litres
per day, rising to 90 million liters per day at peak
times. In addition, work for the wetlands will be
completed by November 2010.
According to Andrew the project which has been labeled
as Anglian Water’s biggest project ever, will continue
to remain a highlight in his working career.
|
|
|
Last Updated:
April 30, 2008
|
|
|
 |