 |
 |
|
|
|
Challenging Views

|
|
YOU will find one of the most beautiful sites in the
Cedar Creek estate situated within the greater Cedar
Lakes environment. This breathtaking area with
elevations of up to 60 metres has amazing views that
stretch as far as the eye can see. To Edwin van
Rensburg from Lidwala Consulting Engineers this site
would be any residents dream but proved to be one of
the most challenging terrains to work on.
|
|
|
The formidable venture which was
requested by the ABSA Development Company started its
construction phase in August 2005. The first
infrastructure project designs for the housing
development began however as far back as 2001. “There
were endless challenges with this project. One of the
biggest stumbling blocks was the registration of the
existing waterways by the Department of Water Affairs
& Forestry (DWAF).”
“DWAF wanted to register the two waterways in the
private development as a public space while the ABSA
Development Company wanted the area to be a private
open space. The matter was later settled in court and
the area was registered as a private space,” explains
Edwin.
Lidwala Consulting Engineers was responsible for the
design of all the services for each of the 440 stands.
They also did the designs for four dams and the
bridge. Besides a challenging infrastructure design
compounded by a steep terrain, the dams alone proved
quite interesting. "Dams had to be resized according
to specific standards and then modelled on Civil
Designer. The program is such a joy to work with as
you can create nifty 3D models for the client and the
landscape architect. It literally all comes to life in
Civil Designer,” he says enthusiastically.
According to Edwin, the road construction proved very
challenging with an average terrain slope of 1 in 5.
To add to this, nearly 2000m³ of rock had to be
excavated. In addition, the contractor had to import
large volumes of material for the construction of the
bridge. “When I say that a lot of material was used
for the construction of the bridge I mean 20 000 cubes
of G5 material to be exact,” notes Edwin almost in
disbelief.
|
 |
Personal |
 |
|
Edwin van Rensburg
Senior Design Technician Edwin van Rensburg has an extensive 19 year track
record which starts at BCP Consulting Engineers as a junior design technician.
After a lengthy 12 year stay, he moved on to PHR Engineers before joining
Lidwala Consulting at the end of 2005.
Edwin has a civil qualification at UNISA and Wits Technikon and is a dad to 3
beautiful daughters. |
|
 |
|
 |
|
|
Working with the initial 2001
survey system presented other problems. “When the
assignment first began, all the data was on one system
and then midway through it had to be imported into
another system. This introduced various bugs which
first had to be cleaned up before the data could be
properly utilised.”
Edwin also assisted with the design of the Cedar Lake
development adjacent to Cedar Creek. “The development
of Cedar Lake was positively received by the residents
of Cedar Creek as it would help reduce the prospect of
illegal squatting. Prior to the development of Cedar
Lake, the area was just a couple of hectares of open
space. Beyond the river however, was a large 20 ha
informal settlement. Residents were afraid that if the
settlement grew, that it would eventually spill over
the river and encroach on their open space.”
The land owner of the informal settlement has tried to
remove the people from his ground to no avail. Cedar
Creek stands range from 900 to 3000 sqm² in size and
are being sold for between R800 000 to R1,2 million
each. The project, valued at about R50 million is
currently in its final phase of completion.
According to Edwin, working with the locals from the
informal settlement was extremely satisfying.
”Although we used mainly conventional construction
methods due to the high volume of earthworks and
excavation that had to be done by machine, we tried to
include labourers from the informal settlement so that
they could take pride in the development. This
presented an ideal solution to the existing crime
problem. Of course we did not expect that all the
electrical cabling would be stolen overnight after it
was installed the previous day,” he says laughing.
Despite the many challenges that the Cedar Creek
development presented, the wealth of knowledge
acquired during the projects near completion is
difficult to match. “I was the RE and the designer on
this project. There are many great moments, but the
greatest of all is seeing your designs come to life
during the construction process. It's a proud moment,”
says Edwin.
|
|
|
Last Updated:
June 09, 2008
|
|
|
 |