 |
 |
|
|
|
MEETING CAPE TOWN’S HOUSING NEEDS

|
|
When it comes to bulk sewer
projects, the sewer design for the N2 Gateway
housing project can definitely be classed in a
league of its own. According to engineers Adrian
Coetzee and Johan Prins from Kwezi V3 Engineers in
Belville, projects like these come but once in a
lifetime.
|
|
|
With the provision of 22 000 new
low income houses, the N2 Gateway project is set to
change the lives of many households living in the N2
informal settlements and is one of the most talked
about assignments in Cape Town with a budget of R2,3
billion.
Some of the factors that led to the N2 Gateway housing
project were the densification
taking place in the catchment area of the Zandvliet
Wastewater Treatment Works as well as overflow
problems experienced in the existing sewer system.
This led to the City of Cape Town inviting tenders for
the design and construction of a new Delft Bulk sewer.
Sobambisana Community Developments, a consortium, was
the successful tenderer and appointed a Joint Venture
Contractor consisting of Asla Construction and Power
Construction, two of the leading construction
companies in the Western Cape.
"We were the leading consulting engineers for
Sobambisana on this Project and handled about 75% of
the design while Bergstan designed the remaining 25%
of the pipeline. The City of Cape Town also appointed
Stewart Scott International to act as project managers
on behalf of the City," explains Project Manager Adrian
Coetzee from Kwezi V3
Engineers.
“The pipeline would have adequate capacity for the new
22 000 homes together with the future sewage flow in
the whole drainage area to the Zandvliet Waste Water
Treatment Works. Since the tender has been awarded to
the Sobambisana Consortium in April 2005, we have been
actively involved with the feasibility phase for the
sewer line and also the final designs on the
project.”
One of the challenges during the design and
construction of the sewer pipe line, was to allow
adequate drainage for all 22 000 homes. Based on the
data obtained in the previous reports, this would
require a pipe of a proportionately large size to be
constructed due to the ground constraints. “We
followed the existing sewer line as this was the
most viable route. This led to the crossing of many large existing services with diameters
of
between 800mm and 2400mm. |
 |
Personal |
 |
|
Johan Prins & Adrian Coetzee
Johan Prins is a Technical Director at Kwezi V3 Engineers Bellville and obtained
his B.Sc B Eng degree at Stellenbosch University.
He is currently a Professional
Engineer and actively involved in bulk water and sewerage services at this
progressive company. Johan is married to Annette and they have four daughters.
Adrian Coetzee is a Project Leader in the Bellville office of Kwezi V3 Engineers
and is responsible for planning, design, contract documentation and construction
supervision. He obtained his B.Tech degree at Cape Peninsula University of
Technology and is currently a Professional Technologist.
Adrian is married to
Mariska and they have twin sons. He enjoys golf, golf and more golf in his
leisure. |
|
 |
|
 |
|
|
“The existing pipeline starts just at the top of
Kuilsriver and Bellville and runs all the way down to
the Zandvliet works. The new pipeline was therefore an
upgrade of the existing line. We conducted the
preliminary designs of the whole pipeline in order to
determine the flow capacity of the first phase where construction could commence,” explains
Adrian, illustrating the scope of the venture.
THE
INVESTIGATION PHASE Collecting
information for the preliminary designs on the project
was problematic due to the fact that most of the team
members that worked on the previous plans no longer work for the
council. “We were lucky to retrieve some of the
original plans from Tygerberg, Oostenberg and even
Stellenbosch Municipalities. We then used the as-built
information together with GIS data of the total
catchment area to create a model with the use of
interactive design package, Civil Designer."
"One of the challenges that we
faced was constructing the sewer line above and below the existing services
while still being able to connect to the works and invert levels. The whole
project was based on the same principle as the existing gravitational
pipeline,” notes Kwezi V3
Technical Director Andre Prins.
The investigation of the venture commenced in July and
lasted till
November 2004 during which time the City of Cape Town
applied for MIG funds from national government. Once
these funds were granted, further investigation
continued on the pipeline’s capacity. The cost
estimate and planned time span on the existing as well
as the adjacent pipeline were based on many
assumptions. According to the technical report, it
would take a period of two years to upgrade and
construct the proposed and existing sewer line.
National government however, wanted the pipeline to be
completed in one year.
“The timeline for the pipeline’s completion was a 12
month construction period which only got going in
December 2005. This meant that the contractor had to
more than double the number of teams in order to meet
the required deadline. This was a challenge but in our
opinion, definitely achievable. At the time of the
interview, the contract was on schedule to be
completed within 12 months,” explains Adrian,
remembering his feedback meeting with the Mayor of
Cape Town in 2005.
CONSTRUCTING THE NEW PIPELINE
According to Adrian, the new pipeline had to be
adequate for flows and it was therefore important to
plan with the assumption that the entire catchment
area would eventually be populated. “The old pipeline,
being between 25 and 30 years old is linked at
various key positions with sluice gate manholes so
that certain sections of the existing manholes could
be shut down to minimize flow."
"This was done in order to allow the existing pipeline
to be refurbished so that it could act as a backup in
the event of an emergency. The sewer pipe will
eventually handle a maximum capacity of 4623 litres
per second in peak wet weather flow at its bottom
section,” says Adrian who worked extensively on the
design.
One of the tender requirements stipulated a quality
assurance plan for each phase of the project, a
document that was stringently followed by the team
during the project's execution. "Our Quality Manager
Pieter Kriel devised a quality control plan for every
task with corresponding checklists and audits with all
the relevant stakeholders. When you are working on an
assignment of this size a QMS document is vital in
order to ensure that tasks are completed correctly,"
explains Andre.
Besides the design challenges, there were numerous
environmental restrictions on the project. “We had to
obtain special permission if we wanted to remove any
of the Heritage, old White Gum trees as well as alien
trees that crossed our path. We therefore used the
services of a botanist, fresh water / river / wetlands
consultant and a dune specialist in order to obtain
the various permissions.”
A section of the housing project has since been
completed with the first few occupants having received
their keys to their homes in the last month. According to
engineers Adrian Coetzee and Johan Prins, projects
like the N2 Gateway come but once in a lifetime and
will be remembered for years to come.
|
|
|
Last Updated:
June 09, 2008
|
|
|
 |