 |
 |
|
|
|
Large Scale Development In The Free State

|
|
The Harrismith office is
bustling with activity as the Phuthaditjhaba and Qwa
Qwa areas are placed in the spotlight for
development projects. The design and implementation
of the venture was re-quested by the
Maluti-a-Phofung Municipality in the beginning of
2003 and Ninham Shand Consulting Engineers
immediately rose to the challenge.
|
|
|
According to Rudi Beeslaar from
Ninham Shand, the project entailed the construction of
a number of gravel distributor roads in Phuthaditjhaba
and Qwa Qwa, as well as the stormwater management in
these areas. “The road that we constructed in the Qwa
Qwa area is 10,3 km in length, of which 9700 meters
include stormwater channels with road crossings,”
explains Rudi.
“The Phuthaditjaba area was equally challenging, as we
constructed a 12,2 km road and the length of
stormwater channels with road crossings was 9500
meters in total. Approximately 100 meters of
storm-water pipes with manholes and outlet structures
were installed,” says Rudi, illustrating the scope of
the project.
Phuthaditjaba is located in the north eastern Free
State Province and is bounded by Kwa-Zulu Natal to the
southeast and Lesothu to the southwest. It has a total
estimated population of 450 000 individuals.
According to Rudi, the existing roads in the area
contrast between two extremes. “The topography of the
region ranges from steep mountainous slopes with
numerous valleys in the south, to rolling hills in the
north. I find that the existing network of roads vary
from tarred roads, to two wheel tracks,” says Rudi.
Road alignments are largely regulated by the existing
landscape. “The horizontal alignment of the roads is
governed by the town-planning layout of the area,
while the vertical alignment was designed to follow
the topographical features with some adjustments in
order to control the storm water run-off,” explains
Rudi, adding that they lay concrete stormwater pipes
with manholes and outlet structures where necessary.
Landscape problems also hampered the development of
the Qwa Qwa road, as the houses are built with no
formal structure. “This presented a great challenge
for the design of the road because it had to be woven
in-between existing homes and we often had to work
with steep gradients,” says Rudi.
|
|
|

The Qwa Qwa ward councils specify
firm guidelines in maintaining standards and act as a
medium between the community and the developer during
the project’s completion. “We found it extremely
challenging to work within the area limitations while
still having to uphold the strict standards as
specified by the ward authorities.”
“Our design was completed in accordance with the
design criteria as set out by the Maluti-a-Phofung
Municipality and in accordance with the Guidelines for
the Provision of Engineering Services and Amenities in
residential township development manual”.
The response from local residents was very
encouraging. “Community reaction on the project was
positive because the undeveloped area was previously
inaccessible, making transportation impossible. With
the new road, everyone’s lifestyle will improve
because people will have the benefit of using taxis,
buses and vehicles for transportation to various
destinations,” explains Rudi.

Currently there is a tendency to
break away from gravel roads because of the shortage
of good gravel in the Qwa Qwa area. This scarcity has
prompted the use of brick paving as an alternative
road surface.
The team at Ninham Shand has supported the
government’s job creation initiative by ensuring that
tasks are as labour intensive as possible. “Layer
works is still being completed by machines, but the
rest of the activities are done by means of manual
labour. The Qwa Qwa region is divided into various
wards and we ensure that we use local workers within
each ward so that the community can obtain maximum
benefit from the project,” says Rudi.
“In addition to this, we try and source material
locally and will probably receive the paving material
from Lancaster, a factory in Qwa Qwa that is
responsible for the manufacture of bricks. Storm water
pipes will also be sourced locally.”
The project has been divided into two phases, with
phase one receiving a budget of R1,2 million for the
creation of 470m of paved road with stormwater
drainage. Phase two will commence shortly and is
expected to receive a budget of R5 million for the
completion of the remaining 1,6km stretch that will
include paving as well as storm water systems.

Rudi explains the design process:
“We used Civil Designer to design the horizontal and
vertical alignments and found the program especially
useful in calculating the cut and fill volumes in the
development of the road. “Once we have completed all
the earthwork on the program, we transfer the
information into AllyCAD so that we can add the
finishing touches to the drawings. We use combination
sheet files to create production drawings for the
contractor.”
When it comes to Civil Designer, Rudi is the resident
expert on the software and assists his colleagues with
various tasks. “I love to help where I can and it
gives me great pleasure to share my knowledge. I have
worked with the software since the days of Stardust
and the program has just grown from strength to
strength,” says Rudi with a smile. |
|
|
Last Updated:
November 02, 2005
|
|
|
 |