 |
 |
|
|
|
The Land Of Engineering Opportunities

|
|
What started out as a career
move for Victor Rieger six years ago with his
relocation to Windhoek has turned out to be one of
the best decisions ever made. Today, Victor is a
proud resident of Namibia and has found the
adjustment from Johannesburg to be surprisingly
easy. "When it comes to large-scale contracts,
Namibia is regarded as the land of engineering
opportunities. I consider myself to be very
fortunate to be working for Windhoek Consulting
Engineer’s Transport division. Work opportunities
here are in abundance," notes Victor, clearly
impressed with developments in his department.
|
|
|
Upgrading of MR 67 between Kamanjap & Omakange
“We are currently working on a very interesting road
upgrade of Main Road 67 between Kamanjap and Omakange
in the north of Namibia. The project was requested by
the Roads Authority of Namibia and consists of 204km
of gravel road that will be upgraded to a bitumen
surface standard.”
“The survey was conducted by Henry Graham surveyors in
Cape Town and entailed a study of the entire servitude
complete with drainage structures. We also performed a
hydraulic investigation of all the bridges and storm
water structures to determine if any structure needed
to be adjusted. We used the information to determine
the horizontal and vertical alignment,” explains
Victor, adding that their primary focus during the
project was to ensure a cost effective design by
optimising the alignment to tie in with the existing
drainage structures along the road.
Although the team enjoyed the project tremendously,
there were many design challenges. “The road was
originally designed with an 80km/h design speed. This
meant that there were a number of cuts and fills that
had to be re-designed in order to accommodate the
increased design speed. In addition, approximately
80km of the road borders the Etosha National Park,
making it a tourist attraction with farms and lodges
along the route.”
“In one particular stretch of approximately 5km, the
steep grades and sharp turns were so severe that the
design speed had to be reduced to 100km/h. We decided
to reduce the design speed due to the environmental
restrictions, as we did not wish to change the
horizontal alignment of the road,” says Victor. The
road design has currently been completed and the
construction, estimated at N$300 million, has been
divided into two sections with the first section
commencing in July 2005.
Victor attributes the success of all his projects to
the speed and efficiency of Civil Designer and admits
to being a loyal user for three years. ”I enjoy
working with the program. It has simplified our lives
to such an extent that we no longer have to spend long
hours trying to create a drawing when the program
performs this operation in a matter of seconds. It has
definitely increased our productivity and we are
always assured of high quality work and a professional
presentation.”
Northern Railway Extension
When Victor speaks about the Northern Railway
Extension, his enthusiasm can hardly be contained.
“This is the biggest project that we’ve ever
undertaken to date. The entire initiative, which has
been divided into three phases, is worth over N$ 1,4
billion.”
The project was requested in response to President Sam
Nujoma’s vision to develop the North of Namibia. This
includes future plans for a new harbour at Cape Fria
on the Skeleton Coast as well as a brand new road and
rail link from Ondangwa to Cape Fria some 800km long.
“We are currently busy constructing the line from
Tsumeb to Ondangwa in phase one of the Northern
Railway Extension. This 245km railway line has an
estimated construction cost of N$850 million and is
expected to be completed in December 2006,” says
Victor.
|
|
|
Aerial photography was used to assist the team with
the alignment, which according to Victor was
challenging to say the least. “Of the 245 km
approximately 88 km falls on commercial farm land. The
remainder of the railway goes through communal land
that is scattered with shacks, schools, graveyards,
kraals, and other obstacles. We conducted a
three-month survey to accumulate the necessary
information for the final horizontal and vertical
design. During the design and even the construction,
changes had to be made to the alignment due to some
burial graves that were encountered. These graves were
not even marked and local residents often had to point
them out to the construction team on site,” explains
Victor.
The first 88km of the project was done using normal
construction methods, while the rest of the venture
was labour intensive. “We used workers to convey sub
ballast material from borrow pits and fill material
from the site onto the embankment. It is likely that
the project will keep us occupied till 2008 and will
generate large-scale employment. In some cases we have
already employed more than 17800 people to assist with
manual labour.”
Phase two of the project entails the construction of a
59km railway line from Ondangwa to Oshikango. The
estimated construction cost is N$ 329 million and is
likely to be completed in December 2007. Similarly,
phase three aims to extend a further 38km railway line
from Ondangwa to Oshakati and has an estimated
construction cost of N$ 220 million. The final phase
of the project will be completed in December 2008.
Windhoek Consulting Engineers has been tasked with the
prestigious responsibility of completing all the
railway work in Namibia, an appointment that has
everyone smiling. ”It is such an incredible privilege
to be working on assignments of this magnitude. The
scope is endless! The earthwork embankment in phase
one is currently 80% complete and we have also since
completed 90km of permanent way construction.”
Does the scope of this venture ever intimidate you?
Victor laughs as he shakes his head. “We are doing big
things in Namibia and I am proud to be part of
something great. Moving here has been the best thing
ever!” |
|
|
Last Updated:
November 02, 2005
|
|
|
 |