|
From time to time, the 9 200-strong
community at Barkly East has lived without water from
October to around December. The meagre local rainfall,
which is below the average for the rest of country,
was just not enough to sustain a yearlong water
supply. In the months leading up to October, the
available water dries up and the boreholes spin into
action. Once they dry up there is simply no more
water.
The project to build an emergency storage dam at
Barkly East was actually approved in 1996, but it was
only in late 2001 that the project finally hit the top
of the priority list. "A project of this kind is not
pure engineering. I spent a lot of time with the
Project Steering Committee in Barkly East ensuring
that the community was happy with the design," says
Tiaan.
"We had commissioned an independent consultant to do
an Environmental Impact Assessment as part of the
process as well. This integrated process did however
ensure that the final design, contractor selection and
labour resources had the backing and commitment of all
parties."
The original plan dictated that the dam was to be
built on ground that was ideal from an engineering
point of view, but that was problematical, as the land
was privately owned. "To avoid all sorts of problems,
the Steering Committee then ruled that the dam had to
be located on council land."
The overflow of the existing water supply dam, and the
water treatment plant sent their recycled water back
into the Langkloof River. There was also an existing
water infrastructure in the area, and it was in these
three factors that Tiaan saw the solutions to
overcoming the tough constraints imposed on the design
by the budget.
"Using the waste water from the treatment plant, and
capturing the overflow water from the existing dam, I
was able to gravitate the water down a line into the
storage dam," said Tiaan. "I also used the existing
pipe and pump infrastructure as well. By using just a
one small extra pump, the storage dam is kept full.
"The dam has a 650m long gravel wall that is 4.8m high
at its highest point. The dam is only 6m deep at its
deepest point. "The maximum capacity of 215 000kl
means that the Barkly East community will now have
water all year round. At a cost of only a paltry
R282.60 per head, the community will profit hugely
from the project."
"The benefits of this project go far beyond the
provision of water all year. The immediate and
long-term advantages to this community are staggering
when you study them, says a proud Tiaan. "The
contractor appointed to do the dam construction is a
local contractor, and the labour force employed on the
project is 100% local. For this area where work is
just a distant dream for most, the employment
opportunities are a godsend."
|
|
|
"Islands are also being built in
the dam and will be stocked with a variety of birds,
to attract tourists who have an interest in birding,"
said Tiaan, a keen birding man himself. "The dam will
also be stocked with trout to attract fishing
tourism."
"In the near future, the quality of life of the
community will be greatly improved by the addition of
water-borne sewerage, which of course for a community
used to having scarce water will be wonderful."
"For me, using CIVIL DESIGNER ROADS as well as
SURVEY+TERRAIN was wonderful. It saved me so much
time, particularly on the earthworks, as we had to
move 40 000m3 from the dam floor to be used in the
wall construction. It is so accurate and easy to use,"
said Tiaan. |