 |
 |
|
|
|
Improved Access To Ugie And Langeni

|
|
"The breathtaking beauty of
the Ugie and Langeni areas is unknown to the rest of
the Eastern Cape because the difficult terrain has
restricted access to this vicinity. With the
completion of the Ugie Langeni Project, this problem
will become a thing of the past and entry into these
areas will no longer be a concern," says Ties Bos,
Managing Director of Saunders and Wium.
|
|
|
The project consists of the
upgrading of existing provincial roads and the
construction of a new section of road in the
Ukhahlamba District of the Elundini Local Municipality
in the Eastern Cape.
The full project was divided into two phases with
phase one comprising of 33km of road from Ugie to
Ncembu. The first leg of the venture was estimated at
a cost of R194 million and was handled jointly by
Steward Scott in Port Elizabeth and Saunders and Wium
in East London as a joint venture.
The New Section of Road
“The road link from Ugie to Langeni is a critical
element of the multi-disciplinary provincial flagship
project, Kei Rail. This project is led by the
Department of Roads and Public Works in the Eastern
Cape and represents an integrated development plan to
stimulate and sustain socio-economic growth in this
region.”
“The construction of the road went out to tender in
November 2003 and the contract was awarded to WBHO /
Mandelethu Joint Venture in March 2004,” explains
Ties.
“The area stretching from Ugie to Langeni is rich in
natural resources and includes agricultural and timber
produce. Large plantations were established some
thirty years ago and harvesting is due to start in the
near future. Since the territory is quite large, the
harvesting cycle will be an ongoing expedition year
after year,” says Ties, explaining that the
construction of the new road will improve access into
the area, allowing farmers to convey their produce to
markets.
The groundwork to the project entailed, inter alia, a
geotechnical study of the area, as well as an
engineering survey of the route. “The relevant data
from the engineering survey was transferred into CIVIL
DESIGNER so that we could create a model of the
terrain. The road was divided into two sections so
that each member of the engineering joint venture
could design their own section. With the help of CIVIL
DESIGNER, we were able to perform all the calculations
with speed, allowing us to optimise cut and fill
volumes,” explains Ties.
In the next 30 months, the contractor aim to complete
approximately 1km of road per month. The road will be
completed with five bridges and several underpasses
for farmers.
In addition, the project requires strict adherence to
environmental criteria, because the road runs through
scenic countryside. “Our project team included
environmental specialists who often engaged in lengthy
discussions on how to overcome the environmental
restrictions imposed.”
|
|
|
“In one instance, an existing farm school was affected
by the new road alignment. Provision was therefore
made in the contract for the construction of school
buildings and sports fields.
Several families will also have to be relocated,
because the new road runs through an existing
village,” says Ties.
“The road is linked to a multi-million rand investment
by the forestry sector at Langeni and will lead to the
creation of employment opportunities for local
residents. This investment involves the annual
harvesting of large quantities of timber in the Ugie
and Maclear area, as well as at Langeni, commencing at
the end of 2006.”
|
|

|
The contract specified the use of
local material and workers during the projects
completion. “This stipulation presented many
challenges because most of the road runs through
farmland, making the acquisition of local labour
extremely difficult. In addition, the nature of the
work requires specific skills and workers will
therefore have to receive extensive training in order
to prepare them for the project.” |
|
“Community reaction on the project is very positive,
as it is aimed at improving the mobility of farmers to
markets and will alleviate the poverty of local
residents through the transfer of skills and training.
Tourism is also likely to receive an economic
injection and entrepreneurs and SMME’s will experience
an increase in job creation opportunities.”
“There are still many months ahead before phase one of
the project will be completed, but the area should
receive significant economic growth after the
completion of the road,” the engineer says in closing.
|
|
|
Last Updated:
November 02, 2005
|
|
|
 |