 |
 |
|
|
|
When Hi-Tech Stormwater And Rural Backwater Meet

|
|
In this township of Tikwana in
the Free State, dongas which they called roads and
which ran like flooded rivers in the wet season, are
now being turned into proper roads. It is a
transformation, which sees one of the most
sophisticated pieces of First World civil
engineering design technology being harnessed to
build roads in some of the most neglected rural
areas of South Africa.
|
|
|
More than 50 000 people in the
region are already feeling the benefit. Tikwana and
neighbouring Hoopstad are typical examples of the
process. Nearest place of any size is Welkom, 60kms
distant.
For NEP Consulting Engineers, the challenge issued by
the local Tswelopele Municipality looked simple
enough: rehabilitate, upgrade and re-surface over 4kms
of roads in Hoopstad itself, and build another 9kms of
new roads in Tikwana to replace existing
disintegrating roads.
In Hoopstad, the work has chiefly involved filling
cracks, re-surfacing and slurry-sealing. In Tikwana,
where the major work had to be done, new asphalt roads
had to be built within the township itself.
“Some of the existing roads in Tikwana were like
dongas. In the rainy weather the flood waters rush
down them – they are like rivers,” says Danie
Kassleman of NEP.
It was not simply a matter of building roads.
“Whatever kind of road you build, there is always
going to be a rainy season, which means storm water,
and the rain has got to go somewhere,” Danie says.
“But how do you provide for this in the most
economical way?”
Using Knowledge Base’s Civil Designer engineering
software package, NEP engineers designed a storm-water
channel into the actual road surface. Along one outer
edge of the 5m-wide asphalt roads in Tikwana, a
1m-wide concrete strip was angled very slightly
downwards so that storm water would naturally collect
and cascade down that edge. The really clever bit is
that traffic can still use this part of the road.
Effectively, it’s a 6m-wide road.
“This represented a saving of over R1-million in the
cost of the project. It meant that we were able to
give the municipality a lot more road for their
money,” Danie says. “Equalizing cut and fill ratios is
always an important costing element in road
construction – in fact, in any civil engineering
enterprise. The software enabled us to establish
quantities very easily, and we reached a good balance
of cut and fill.
|
|
|
“Our biggest problems were
concerned with storm-water. Obviously, we couldn’t
fight it. So we decided to use a formula, which NEP
has adopted in the past, where similar problems arose
– bringing the fall of storm-water to one side of the
road and controlling it that way. Civil Designer was
very useful in helping us to design the correct levels
that would ensure that storm-water would be steered
away from the immediate area to where it could do no
harm or become a health hazard.”
Civil Designer’s inter-active Storm, Water and Roads
design modules were harnessed to produce the drawings,
surface modelling and final design of the roads. Danie
points out, however, that NEP’s
“road-which-is-also-a-storm water channel” has been
designed essentially for internal roads, where speeds
are normally not high.
The project was funded by the Consolidated Municipal
Infrastructure Programme (CMIP). |
|
|
Last Updated:
November 02, 2005
|
|
|
 |