 |
 |
|
|
|
The Mfuleni Bulk Earthworks Project

|
|
Liebenberg & Stander was
commissioned by the City of Cape Town (Tygerburg
Administration) to handle the design, construction
monitoring and contract administration of the
Mfuleni Bulk Earthworks contract.
|
|
|
Marthinus Retief, a Candidate
Engineer who worked closely on the project, describes
his involvement. “This was my first participation in a
project of this nature and I found it to be an
interesting learning experience. We liaised with the
environmental town planners and other relevant bodies
to develop the 80 hectares of land required to create
4000 new erven for residential use”.
“This involved shaping the existing dunes to
accommodate future township services. The design of
the earthworks platform had to take cognisance of the
50 year Kuils River flood line that fixed levels on
the west side of the site, as well as the integrated
stormwater and road concept designs. We minimised
infrastructure costs by optimising land use”.
“Dumper trucks and excavators were used to move 850
000m³ of earth on the 80 hectares,” Marthinus
explains.
“We followed a systematic procedure that started with
a survey of the existing terrain, and involved a
concept study of the stormwater overland flow. The
information was then transferred into Civil Designer
where a model of the bulk earthworks platform was
created with the use of the Survey + Terrain module”.

“Points were inserted into the model so that the cut
and fill volumes could be calculated accurately in
order to optimise the mass haul cartage and eliminate
the import and export of material. The program allowed
me to create contours and move points around. I found
the quick contour function to be very helpful during
this phase,” says Marthinus smiling.
|
|
|
“During the cutting process, care
was taken on the use and handling of topsoil. In order
to prevent increased costs for stockpiling, the cut
topsoil was immediately used on fill areas and then
spread to final levels. This promoted soil fertility
and resulted in lots of green growth during the winter
months. In addition, we ploughed straw into the top
100mm of finished platform levels to stablise soil and
prevent wind erosion. It helped that the project was
completed during a rainy winter, as this aided the
compaction of soil”.
The team at Liebenberg & Stander found an alternative
use for the trees and shrubs that were cleared from
the ground. “Instead of dumping this, we tried to
prevent waste by using the trees and shrubs to supply
fire wood for the local community during winter. The
remaining shrubs were further used to create wind
barriers and to stabilise soil where the design
platform banked onto existing ground levels”.
|
|

|
“My primary objective during the
design of the bulk earthworks was to create a platform
with high and low points so that there would be
sufficient drainage and thereby create an area
conducive for residential use. This involved long
discussions with town planners so that enough space
could be created for school sites, retention ponds and
open spaces. Looking back, I feel that this objective
was met,” Marthinus says. |
|
When asked what his most rewarding experience was
during the five-month project, Marthinus says
enthusiastically: “it definitely was seeing the
finished earthworks project and being part of a
process of creating 4000 new homes for families and a
pleasant living space for the community”.
|
|
|
Last Updated:
November 02, 2005
|
|
|
 |