 |
 |
|
|
|
"Ambition Is Not Enough"

|
|
Although Kwezi Mpuhlu is an
incredibly ambitious man, he understands the
difference between ambition and the solid hard work
required to get the job done. "Ambition is a good
thing, but it is not enough," says Kwezi, "it takes
team work and good planning to achieve your goals."
These are the words of one of MBSA Consulting’s
dynamic new partners.
|
|
|
Most of MBSA’s projects are water
and road related. “We tend to concentrate on rural
access roads, rural water schemes and bulk water
supplies. In all cases we make use of Civil Designer
and AllyCAD to fulfil our design needs. We are also in
the process of employing more students so that we can
teach them how to use the program and thereby create
additional backup staff for projects.”
One of the ventures that MBSA is currently working on
is the Hota-Mbewula bulk water scheme project. “We
have just completed the preliminary designs for the
water scheme and submitted these to the client. The
idea is to make water accessible to rural areas, which
means that there is a greater commitment towards
spring water protection. This activity entails the
collection of water from mountain springs and the
construction of water purification reservoirs for
reticulation purposes. The process requires no power
as the entire procedure makes use of gravity. Once we
have sized the pipes, we make use of AllyCAD to
complete the design.”

The bulk water scheme project was
requested by the Chris Hane Dristrict Municipality and
is estimated at a cost of R5 million. “Our appointment
during this initiative involved the preparation of a
business plan in accordance with DWAF requirements.
This plan was presented electronically via an online
web-based system. Other responsibilities on the
project included a feasibility study, the scoping
report, the construction license application as well
as some water availability testing. We submitted the
business plan in March 2004 and have since completed
the project designs,” explains Kwezi, adding that the
construction phase is due to happen in July 2005.
According to Kwezi, one of the most challenging areas
during the project’s completion was community
involvement. “When it comes to community involvement,
your negotiation and presentation skills are tested to
the maximum. It is not always viable to start a new
venture without getting complete acceptance from the
community. You therefore have to explain the benefits
of the project and get the community to support it or
else risk failure. The trick is to have good relations
with the area ward councillor and to work very closely
with them on any new venture.”
|
|
|
Kwezi regards himself as one of Civil Designer and
AllyCAD’s greatest fans. “We use these programs in all
our projects and I have no complaints. What I
particularly like about Civil Designer is that you get
everything you need in one package. We use the program
for existing roads projects and tender for new road
upgrades every three weeks. The surveys for road
projects are done externally and the information is
then used to determine the correct alignments for new
access roads. We are currently working on a 10km road
upgrade valued at R3 million, a project which will be
child’s play for a program like Civil Designer.”
Fort Brown Bulk Water Supply
The Fort Brown bulk water supply project is a venture
of a different kind. “This project was requested by
the Makana Municipality in Grahamstown and is
currently in its commission phase. The main aim of the
project is to supply bulk water to rural areas, as
households currently have to walk 200 metres just to
get water. This situation is not viable at all, so
people are very happy that the project is finally in
place,” explains Kwezi.
|
|

|
One of the project requirements
specified the use of unskilled local labour. “The
project was extremely labour intensive and helped the
community with job creation. We used unskilled workers
to help with the water supply and appointed a
consultant to supervise the process. This arrangement
turned out to be a win-win situation as community
members were taught how to provide water for
themselves and acquired much needed income and
invaluable skills in the process,” says Kwezi, adding
that the feasibility test was conducted in January
2004.
|
|
Due to its sizable scope, the
project was divided into two phases. “The first half
of the assignment entailed the extraction of water
from the river to portable purification plants. Water
was then stored in containers and filtered through a
chemical process. We started phase one in September
2004 and it has since been completed in February 2005.
The total cost for phase one is R1 million.”
Project environmentalists proved to be yet another
challenge. “We had to submit a scoping report in order
to conform to regulations. Some of the farmers fenced
off a portion of their land, which meant that the
construction team had to avoid this area completely.
This led to numerous public participation and site
meetings and we were watched very closely. But in
every project one has to learn to rise above the
challenges,” says Kwezi positively.
“In phase two of the project we plan to build an agri
village. Agri villages are smallholdings where
community members are allocated small plots of land
for grazing and services. The cost of phase two is
estimated at R15 million and is likely to be completed
in 2007.
Although Kwezi’s last few years have been extremely
eventful, his long-term goal remains modest. “I hope
to graduate with my MBA at the end of 2005 and then
pursue my Masters in Engineering at the University of
Cape Town. I would also like to learn as much as I can
and continue to make a positive difference in my
community,” he says smiling with contentment. |
|
|
Last Updated:
November 02, 2005
|
|
|
 |