|
"We work in a wide circle around
Kimberley, roughly 200km in any direction," he says in
his quiet unhurried manner. The countryside in the
Northern Cape, of which Kimberley is the capital, is
harsh and scrubby. A region of extremes, the high
temperatures have spawned towns with names like Hotazel, while shattered rocks are stark testimony to
the freezing temperatures on winter nights.
"We are doing the earthworks for the building
platforms at the new Kimberley prison. It's a
straightforward job for us, it's just a very big
project. There was a huge amount of sand that had to
be moved. The first 600mm needed to be removed, as it
could not do the job. We then had to remove the earth
under that and create the platform with the
lower-level ground."
The Kimberly prison job is not difficult. "It is
basically one building duplicated 15 times - they are
all built on the same principle. We are importing
approximately 100 000 cubic meters of material. We
specified a G5 material, and it was all available in
the vicinity."
"In Kimberly, the biggest challenge we face is the
flat terrain. We have to lift the roads out of the
ground, sometimes up to half a meter. To compensate,
we have to raise the level of the erven next to the
roads. We have to do this otherwise the sewerage and
water just won't work."
"Storm water systems are very problematic for us. The
only way to get the water away is to raise the roads
so that you create the minimum slope required. To make
sure the sewer doesn't go too deep, we make use of
strategically placed sewerage pump stations. The sewer
pipes usually don't go deeper than 5-6m, which is
acceptable to us if you compare them to Northern Cape
benchmarks."
MVD has just completed a development in Hopetown
consisting of 100 RDP houses. Digging the trenches for
the sewer pipes posed some interesting problems. "The
municipality doesn't have mechanical resources, so
they do the digging work with whatever they have,
normally spades and jackhammers. It created a bit of a
crisis as they hit limestone banks, which are layered.
Blasting is extremely difficult as the blast seldom
removes what was intended; it's just the nature of the
material. The only way around this is to use
jackhammers, and that is time consuming and really
hard work."
The depth of the trenches creates more problems. "As
soon as the depth gets to 3.5m, it is dangerous for
workers to be in there, so we have to taper the sides.
To give you an idea of how flat it is, over a distance
of 350m we only have a 900mm slope, which is nothing,"
he says. |
|
|
The firm invests in Civil Designer training. "Civil
Designer is an excellent design programme, and the
training is really good. We recently benefited from
the training on an 8km road project in Kuruman. We dug
a series of test holes and divided the road up into
sections and worked out separate layer-works for each
chainage. Civil Designer really helped us with that;
it saved us a lot of time. We created profiles for
each section, for example we said from 0-400 the
layer-works looks like that, and so on."
Most of the projects are of a similar size and
difficulty. But there has been a boom over the last
two years and the firm has been able to exploit the
demand for housing in the region. There are also a
number of big jobs on the order book for 2005. The
demand is driven by a long awaited economic revival in
the Northern Cape. "Two big shopping complexes are
about to rise out of the dusty ground; both are more
than 20 000m2. "There have been lots of legal issues
on those but they are ready to go now and we are
involved in both."
Local newspaper headline writers have enjoyed the one
project. 'Waterfront to be built with no Waterfront,'
trumpets the one ironically. "On that project we
basically took the architectural designs, and did all
the mass earthworks, creating a variety of slopes and
levels to see what the cost implications were. That
project has been subject to lots of changes and
controversy, but they are now building about 26 000m2
of just retail space."
The second complex, situated on the Cape Town road,
was also bedevilled by zoning and other legal issues.
"This was finally approved late in December 2004 and
building will start soon. We are involved with both
these projects to different degrees. The Waterfront
project is a small one for us, but the second one is a
major project, and of course Civil Designer will be
used to save us time and money."
The great sky that covers the huge area that MVD
covers doesn't often have rain clouds decorating the
endless blue. As you get out of the car, you are
almost assaulted by the silence. It is deafening.
Maybe that’s why Dirk speaks so quietly.
|