 |
 |
|
|
|
Ten Year Water Supply Plan for the Insika Yethu
Municipal Area

|
|
For the people in the Insika
Yethu Municipal area, collecting water is very hard
work. Approximately 75% of the population relies on
rivers, springs and small open dams for their water
supply. This figure is likely to drop to 55% with
the completion of the current water network
projects.
|
|
|
The next phase of the venture
includes an extensive feasibility study that was
conducted by Camdekon Consulting Engineers in June
2002. The findings and recommendations of the study
were presented in April 2004 and provided options for
domestic water supply in the Insika Yethu Municipal (IYM)
area in the Chris Hani District.
According to Vumile Jack, Camdekon Civil Engineering
Technician, the project should provide large-scale
employment opportunities in the area and will
dramatically improve the living conditions of
residents.
“The IYM area, which comprises of the Cofimvaba and
Tsomo districts, is served by 46 councillors and
consists of 23 wards and 375 rural settlements. The
current population is estimated at 240 089 individuals
and 44000 households, while the terrain covers 4226
km˛ with elevations varying between 500m and 1400m
above sea level,” says Vumile.
During the feasibility study, the team worked closely
with a GIS consultant in order to extract maps of the
area. “We start the project by studying topographical
maps of the region so that we can establish the
boundaries to the local municipality and at the same
time collect vital information that is required for
input into the system.”

|
|
|
“We then accumulate information on
the current situation pertaining to water provision
and collect additional data from other consultants so
that water infrastructure can be planned. Information
is usually received in hard copy and then input into
CIVIL DESIGNER so that we can create the design.”
The production of water scheme and supply network
drawings is completed with the use of AllyCAD. “I find
the program to be very easy to use and there are many
shortcuts that allows one to complete projects quickly
and effectively,” says Vumile.
The next phase of the project involved exploratory
analysis. “We contracted SRK consultants in order to
conduct an exploratory study of the area’s ground
water, so that they could establish if there was
enough water to develop the schemes for the region.
The study depicts how much water each borehole
produces, as well as the extent and number of
potential well field areas. This investigation
specifically looks at the estimated yield so that all
information pertaining to the area’s potential water
wealth can be summarized in map format.”

The water consumption is based on
130 litres per person per day in urban areas and 25
litres per person per day in rural areas.
Vumile explained the abstraction of water as follows:
“The amount abstracted from boreholes is largely
dependant on the yield and recharge of the borehole,
as well the daily water demand for the community.”
Area information accumulated, revealed that there are
14 potential ground water boreholes with approximately
3-5 boreholes per scheme. “This equates to about 40 –
70 boreholes that pump to reservoirs. In terms of the
ground water potential, the exploration program
identified target well fields where boreholes of
yields in excess of 1,5 litres per second can be
expected. The target zones are geographically
favourable for the development of well fields in
undeveloped areas.”
In addition to this, the district has adequate surface
water resources particularly toward the east where
runoff riverflows are able to supply domestic and
stock needs. “Four large dams are located in the area
with reserve capacity to supply all domestic
requirements, while a few perennial springs with
yields of up to 5 litres per second were identified.”
“These dams were constructed for irrigation purposes
and are largely underutilized in the Transkei area
with only one dam being used for domestic water
supply. Agriculture is a major economic activity in
the area and these irrigation schemes are therefore
being developed with a total planned irrigated area of
10 000 hectare,” explains Vumile.
|
|
 |
Pollution Control Technologies also
carried out an Environmental Impact Assessment study
during the project, in order to determine the runoff
river reserve as well as any negative impact that the
development could bring about to the environment.
“The feasibility study found that it was more cost
effective to operate and maintain groundwater schemes
as opposed to surface water schemes. This was largely
due to the sophisticated equipment and materials used
in a surface water scheme. The cost of developing the
water schemes was estimated at R220 million.” |
|
Although Vumile spent many long hours on the project,
he is pleased with his involvement and looks forward
to the next challenge. “The feasibility analysis was
very interesting and we learnt a great deal about the
area and its people. The existing schemes should be
completed by the end of 2007, while new schemes are
planned for completion by 2015. Inhabitants of the
Insika Yethu Municipal area can therefore expect
positive change in the next ten years,” he says
proudly.
|
|
|
Last Updated:
November 02, 2005
|
|
|
 |